July 19th – Following the canal breach a few weeks ago, that saw the local canals lose nearly a foot in level following a breach into a culvert beneath the waterway at Little Bloxwich, the repair has been effected and levels are back up to a healthy level now.

At Clayhanger, the low end of the overflow is now running well and it’s a fine sight and sound once more.

June 12th – Following isolation of the leak at Little Bloxwich, the canal level has continued to rise and is now about 20-25mm off maximum (ie. the weir bar at Clayhanger overflow), so more or less back to normal.

It took a while, with problems at Chasewater and with balancing pumps having to be installed at the leak site, but thankfully, apart from the fact that there’s a large repair required in Little Bloxwhich which will prevent passage from Brownhills to Wolverhampton and vice versa by boat for a bit, it’s good to see the waterway back to normal health.

This could have been so much worse.

June 2nd – Heading out on a dull but warm afternoon, the eventual aim was Draycott in the Clay steam fair at Klondyke Mill, but fate had other ideas. On the way, I called in at Chasewater to see if it was filling the canal. It was, the valves were open.

There has been a leak in the canal near Little Bloxwich that has lost a huge amount of water into a culvert beneath the canal, and the Canal and River Trust had said initially the drop in level was due to Chasewater’s supply being cut off by Staffordshire County Council, which was clearly arrant nonsense.

The Trust finally released an emergency stoppage notice and began damming off the leak that very afternoon.

You can read more here.

Chasewater is still very full, and when called upon will need to fill the five inches or more lost from the canal. An interesting situation to watch.